Hart Innovative Solutions - Project Plan for Plant Reconfiguration


Project Start Date: Sun 8/8/99
Project Finish Date: Mon 4/10/00

Tasks with Assignments

IDTask NameWorkDurationStartFinish% Work Complete
1Start Plant Reconfiguration Project - Construction, Moves and Rearrangements0 hrs0 daysWed 9/1/99Wed 9/1/99100%
2Phase I: Project Initiation20 hrs27 daysMon 8/9/99Tue 9/14/9928%
3Sponsorship: Define needs and determine expectations for ongoing updates and support. 4 hrs2.6 daysWed 9/1/99Fri 9/10/9960%
1IE Hart- Greg4 hrs Wed 9/8/99Fri 9/10/9960%
4Resources: Identify project resources, and contacts. Clarify roles and responsibilities.2 hrs1 dayMon 8/9/99Mon 8/9/9940%
1IE Hart- Greg2 hrs Mon 8/9/99Mon 8/9/9940%
5Project Background: Interview to obtain background on plant expansion project and company. Discuss status, plans, progress and expected results.8 hrs1 dayWed 9/1/99Wed 9/8/9930%
1IE Hart- Greg8 hrs Wed 9/8/99Wed 9/8/9930%
6Strategies & Assumptions: Identify measurable goals, objectives, case for action, applicable strategies, assumptions, constraints, and criteria.6 hrs3 daysWed 9/8/99Tue 9/14/990%
1IE Hart- Greg6 hrs Fri 9/10/99Tue 9/14/990%
7Phase II: Plan Macro Layout and Plant Addition. Obtain Approvals.43.2 hrs5 daysWed 9/15/99Tue 9/21/9913%
8Macro Layout Inputs: Review / collect input on macro space needs and department interdependencies – material and communications flow.12 hrs3 daysWed 9/15/99Fri 9/17/9910%
1IE Hart- Greg12 hrs Wed 9/15/99Fri 9/17/9910%
9Shared Areas: Determine optimum locations for cafeteria, restrooms, corridors and other shared space. 15.2 hrs1 dayMon 9/20/99Mon 9/20/9930%
2AR Architect8 hrs Mon 9/20/99Mon 9/20/9930%
1IE Hart- Greg4 hrs Mon 9/20/99Mon 9/20/9930%
9CL Plant Manager1.6 hrs Mon 9/20/99Mon 9/20/9930%
10CL Operations Manager1.6 hrs Mon 9/20/99Mon 9/20/9930%
10Macro Layout: Prepare macro layout including department / work areas, shared areas, aisles, interior walls and doors.8 hrs0.5 daysTue 9/21/99Tue 9/21/990%
2AR Architect4 hrs Tue 9/21/99Tue 9/21/990%
1IE Hart- Greg4 hrs Tue 9/21/99Tue 9/21/990%
11Construction Permits: Obtain approval of town zoning commission and any other necessary agencies to proceed with construction.8 hrs0.5 daysTue 9/21/99Tue 9/21/990%
2AR Architect4 hrs Tue 9/21/99Tue 9/21/990%
9CL Plant Manager4 hrs Tue 9/21/99Tue 9/21/990%
12 Phase III: Define Micro Plant Layout188 hrs56.33 daysMon 8/9/99Tue 10/26/990%
13Resource Identification: Identify department managers and other plant personnel to provide detailed input on layout.4.8 hrs1 dayFri 9/24/99Mon 9/27/990%
1IE Hart- Greg4 hrs Fri 9/24/99Mon 9/27/990%
14HR Human Resources Mgr.0.8 hrs Fri 9/24/99Mon 9/27/990%
14Detailed requirements: Conduct reviews with identified personnel. Identify specific needs. Identify current problem areas and identify improvements. 40 hrs17 daysMon 9/27/99Wed 10/20/990%
1IE Hart- Greg20 hrs Mon 9/27/99Mon 10/4/990%
10CL Operations Manager8 hrs Mon 9/27/99Mon 10/4/990%
11CL Process Engineer12 hrs Mon 9/27/99Mon 10/4/990%
15Dept. Interactions: Clarify and optimize interactions and relationships between departments and support functions.8 hrs4 daysWed 10/20/99Tue 10/26/990%
1IE Hart- Greg8 hrs Wed 10/20/99Tue 10/26/990%
16Equipment Inventory: Inventory equipment and furniture. Assign individual numbers to facilitate move coordination. 56 hrs10 daysMon 8/9/99Fri 8/20/990%
1IE Hart- Greg40 hrs Mon 8/9/99Fri 8/20/990%
11CL Process Engineer16 hrs Mon 8/9/99Fri 8/20/990%
17Equipment Drawings: Measure equipment and furniture footprints and develop CAD templates. Take digital photos. 4 hrs1 dayMon 8/9/99Mon 8/9/990%
1IE Hart- Greg4 hrs Mon 8/9/99Mon 8/9/990%
18Equipment Needs: Identify equipment needs including move special handling and hookup requirements (electrical, exhaust, air, vacuum, water, etc.)1.6 hrs1 dayMon 8/9/99Mon 8/9/990%
1IE Hart- Greg1.6 hrs Mon 8/9/99Mon 8/9/990%
19Equipment Database: Marry CAD drawing, equipment basics and digital photos in database.4 hrs1 dayMon 8/9/99Mon 8/9/990%
1IE Hart- Greg4 hrs Mon 8/9/99Mon 8/9/990%
20Flexibility: Design flexibility into the layout including such things as quick release hook-ups, standard services grid, and air pallets.6.4 hrs1 dayTue 9/21/99Tue 9/21/990%
1IE Hart- Greg3.2 hrs Tue 9/21/99Tue 9/21/990%
2AR Architect3.2 hrs Tue 9/21/99Tue 9/21/990%
21Preliminary Micro Layout: Define layout based on input. Prepare CAD layout options for review.48 hrs5 daysMon 8/9/99Fri 8/13/990%
1IE Hart- Greg40 hrs Mon 8/9/99Fri 8/13/990%
2AR Architect8 hrs Mon 8/9/99Fri 8/13/990%
22Preliminary Layout Selection: Evaluate preliminary layout options vs. assumptions, constraints and criteria. Select a layout.15.2 hrs2 daysMon 8/16/99Tue 8/17/990%
1IE Hart- Greg8 hrs Mon 8/16/99Tue 8/17/990%
9CL Plant Manager2.4 hrs Mon 8/16/99Tue 8/17/990%
10CL Operations Manager2.4 hrs Mon 8/16/99Tue 8/17/990%
11CL Process Engineer2.4 hrs Mon 8/16/99Tue 8/17/990%
23Phase IV: Design Construction and Utilities for Addition0 hrs1 dayMon 8/9/99Mon 8/9/990%
24Construction Design: Design placement of walls and building features such as staircase, cafeteria, locker rooms and bathrooms0 hrs1 dayMon 8/9/99Mon 8/9/990%
25Foundation and Concrete Floor Design Design: Designfootings for construction and concrete floor for new building.0 hrs1 dayMon 8/9/99Mon 8/9/990%
26Floor Coverings: Design and select floor coverings including tiles and carpeting - consider conductive.0 hrs1 dayMon 8/9/99Mon 8/9/990%
27Ceiling treatment: Design drop ceiling - consider non-particulate ceiling tiles.0 hrs1 dayMon 8/9/99Mon 8/9/990%
28Electrical Design: Design electrical grid, buss bar(s), drops and wall plugs.0 hrs1 dayMon 8/9/99Mon 8/9/990%
29Electrical Design: Design electrical grid, buss bar(s), drops and wall plugs.0 hrs1 dayMon 8/9/99Mon 8/9/990%
30HVAC Design: Design HVAC trunk line, branches, vents and machine exhaust0 hrs1 dayMon 8/9/99Mon 8/9/990%
31EPA Approvals: Obtain EPA approvals for roof penetrations and exhaust.0 hrs1 dayMon 8/9/99Mon 8/9/990%
32Plumbing Design: Design water input and drains, plumbing and bathroom fixtures.0 hrs1 dayMon 8/9/99Mon 8/9/990%
33Phase V: Prepare Plan, Bids and Budget for Project704.8 hrs86.33 daysMon 8/9/99Tue 12/7/990%
34Project Plan Inputs: Meet with selected contractors and subcontractors. Define activities, timing, resources, information needs and interfaces.104 hrs5 daysTue 9/14/99Tue 9/21/990%
1IE Hart- Greg20 hrs Tue 9/14/99Tue 9/21/990%
2AR Architect20 hrs Tue 9/14/99Tue 9/21/990%
3PC Prime Contractor8 hrs Tue 9/14/99Tue 9/21/990%
4SC HVAC Subcontractor8 hrs Tue 9/14/99Tue 9/21/990%
5SC Electrical Subcontractor8 hrs Tue 9/14/99Tue 9/21/990%
6SC Plumbing Subcontractor8 hrs Tue 9/14/99Tue 9/21/990%
7SC Carpenters12 hrs Tue 9/14/99Tue 9/21/990%
8SC Drywall Installers12 hrs Tue 9/14/99Tue 9/21/990%
12SC Site Prep Concrete Subcontractor8 hrs Tue 9/14/99Tue 9/21/990%
35Integrated Project Plan: Create an integrated project plan for construction, preparing for occupancy, personnel and equipment moves.33.6 hrs3 daysTue 9/21/99Fri 9/24/990%
1IE Hart- Greg12 hrs Tue 9/21/99Fri 9/24/990%
2AR Architect9.6 hrs Tue 9/21/99Fri 9/24/990%
3PC Prime Contractor12 hrs Tue 9/21/99Fri 9/24/990%
36Bid Approach: Decide approach for bidding - prime contractors with bids to subs, subcontractors assigned to prime contractor, other.8 hrs0.33 daysMon 8/9/99Mon 8/9/990%
2AR Architect2.67 hrs Mon 8/9/99Mon 8/9/990%
1IE Hart- Greg2.67 hrs Mon 8/9/99Mon 8/9/990%
9CL Plant Manager2.67 hrs Mon 8/9/99Mon 8/9/990%
37Bid Criteria: Bid team of architect, consultant and sponsors provide input on evaluation criteria for contractors – cost, quality, and record of performance. 46.4 hrs4 daysMon 8/9/99Fri 8/13/990%
2AR Architect32 hrs Mon 8/9/99Fri 8/13/990%
9CL Plant Manager4.8 hrs Mon 8/9/99Fri 8/13/990%
1IE Hart- Greg9.6 hrs Mon 8/9/99Fri 8/13/990%
38Bid Submission: Prepare and submit bid packages to selected contractors and subcontractors.Select contractors based on estimates and other criteria. 116 hrs22 daysFri 8/13/99Tue 9/14/990%
2AR Architect80 hrs Fri 8/13/99Fri 8/27/990%
1IE Hart- Greg24 hrs Fri 8/13/99Tue 9/14/990%
9CL Plant Manager12 hrs Fri 8/13/99Fri 8/27/990%
39Project Budget: Prepare a detailed budget to track project expenditures. Build in contingency for unanticipated developments and changes. 28.8 hrs4 daysTue 9/14/99Mon 9/20/990%
1IE Hart- Greg16 hrs Tue 9/14/99Mon 9/20/990%
2AR Architect12.8 hrs Tue 9/14/99Mon 9/20/990%
40Start Construction: Break ground. Commence work on addition.0 hrs0 daysFri 9/24/99Fri 9/24/990%
41Project Coordination: Coordinate work of prime contractor and subcontractors.Manage changes. 288 hrs52 daysFri 9/24/99Tue 12/7/990%
3PC Prime Contractor160 hrs Fri 9/24/99Fri 11/19/990%
1IE Hart- Greg64 hrs Fri 9/24/99Fri 11/19/990%
2AR Architect64 hrs Fri 9/24/99Fri 11/19/990%
42Project Tracking: Track activity completion on project plan. Track expenditures vs. budget.80 hrs37 daysFri 9/24/99Tue 11/16/990%
3PC Prime Contractor40 hrs Fri 9/24/99Fri 10/29/990%
1IE Hart- Greg20 hrs Fri 9/24/99Fri 10/29/990%
2AR Architect20 hrs Fri 9/24/99Fri 10/29/990%
43Phase VI: Construct Plant Addition249.2 hrs7 daysMon 8/9/99Tue 8/17/990%
44Foundation: Excavate and pour foundation for new building.14.4 hrs2 daysMon 8/9/99Tue 8/10/990%
12SC Site Prep Concrete Subcontractor12.8 hrs Mon 8/9/99Tue 8/10/990%
3PC Prime Contractor1.6 hrs Mon 8/9/99Tue 8/10/990%
45Exterior Framing: Frame exterior walls and roof trusses for new building.30.4 hrs4 daysMon 8/9/99Thu 8/12/990%
7SC Carpenters27.2 hrs Mon 8/9/99Thu 8/12/990%
3PC Prime Contractor3.2 hrs Mon 8/9/99Thu 8/12/990%
46Roofing: Install roof for new building.38 hrs5 daysMon 8/9/99Fri 8/13/990%
13SC Roofers34 hrs Mon 8/9/99Fri 8/13/990%
3PC Prime Contractor4 hrs Mon 8/9/99Fri 8/13/990%
47Exterior Walls: Construct exterior walls with panels insulation.53.2 hrs7 daysMon 8/9/99Tue 8/17/990%
7SC Carpenters47.6 hrs Mon 8/9/99Tue 8/17/990%
3PC Prime Contractor5.6 hrs Mon 8/9/99Tue 8/17/990%
48Rough Electrical: Rough in electrical grid,exterior wall wiring, boxes and infrastructure38 hrs5 daysMon 8/9/99Fri 8/13/990%
5SC Electrical Subcontractor34 hrs Mon 8/9/99Fri 8/13/990%
3PC Prime Contractor4 hrs Mon 8/9/99Fri 8/13/990%
49Rough HVAC: Install HVAC trunk lines and branches.30.4 hrs4 daysMon 8/9/99Thu 8/12/990%
4SC HVAC Subcontractor27.2 hrs Mon 8/9/99Thu 8/12/990%
3PC Prime Contractor3.2 hrs Mon 8/9/99Thu 8/12/990%
50Rough Plumbing: Install pipes for water mains and branches.30.4 hrs4 daysMon 8/9/99Thu 8/12/990%
6SC Plumbing Subcontractor27.2 hrs Mon 8/9/99Thu 8/12/990%
3PC Prime Contractor3.2 hrs Mon 8/9/99Thu 8/12/990%
51Concrete Floor: Pour and level concrete floor for new building.14.4 hrs2 daysMon 8/9/99Tue 8/10/990%
12SC Site Prep Concrete Subcontractor12.8 hrs Mon 8/9/99Tue 8/10/990%
3PC Prime Contractor1.6 hrs Mon 8/9/99Tue 8/10/990%
52Phase VII: Complete Addition Interior Construction44 hrs7 daysMon 8/9/99Tue 8/17/990%
53Interior Walls Framing: Frame interior walls6.8 hrs0.89 daysMon 8/9/99Mon 8/9/990%
7SC Carpenters6.08 hrs Mon 8/9/99Mon 8/9/990%
3PC Prime Contractor0.72 hrs Mon 8/9/99Mon 8/9/990%
54Interior Walls Electrical: Install electrical wiring and boxes in interior walls.6.8 hrs0.89 daysMon 8/9/99Mon 8/9/990%
5SC Electrical Subcontractor6.08 hrs Mon 8/9/99Mon 8/9/990%
3PC Prime Contractor0.72 hrs Mon 8/9/99Mon 8/9/990%
55Interior Walls Finishing: Install insulation and dry wall on interior walls. Tape and sand.6.8 hrs0.89 daysMon 8/9/99Mon 8/9/990%
8SC Drywall Installers6.08 hrs Mon 8/9/99Mon 8/9/990%
3PC Prime Contractor0.72 hrs Mon 8/9/99Mon 8/9/990%
56Painting: Paint walls and trim.6.8 hrs0.89 daysMon 8/9/99Mon 8/9/990%
15SC Painters6.08 hrs Mon 8/9/99Mon 8/9/990%
3PC Prime Contractor0.72 hrs Mon 8/9/99Mon 8/9/990%
57Bathrooms: Construct bathrooms, partitions, plumbing and fixtures0 hrs1 dayMon 8/9/99Mon 8/9/990%
58Floor Tile: Install tile on floor0 hrs1 dayMon 8/9/99Mon 8/9/990%
59Carpet: Install carpet as required - consider conductive, low pile carpet0 hrs1 dayMon 8/9/99Mon 8/9/990%
60Punch List: Prepare punch list of corrective actions and follow through to ensure completion.16.8 hrs7 daysMon 8/9/99Tue 8/17/990%
1IE Hart- Greg16.8 hrs Mon 8/9/99Tue 8/17/990%
61 PhaseVIII: Review and Improve Manufacturing Processes185.2 hrs34 daysMon 8/9/99Thu 9/23/990%
62Schedule Review: Review process and customer requirements for each product line. Determine takt time, cycle time and capacity vs. load.36 hrs17 daysMon 8/9/99Tue 8/31/990%
1IE Hart- Greg20 hrs Mon 8/9/99Fri 8/13/990%
11CL Process Engineer16 hrs Mon 8/9/99Fri 8/13/990%
63Quality: Obtain data on quality and defects. Define ways to improve quality and reduce defects.6.4 hrs9 daysWed 9/1/99Mon 9/13/990%
1IE Hart- Greg6.4 hrs Wed 9/8/99Mon 9/13/990%
64Process Observation: Observe manufacturing operations to ensure layout incorporates best possible operating methods.20 hrs5 daysTue 9/14/99Mon 9/20/990%
1IE Hart- Greg20 hrs Tue 9/14/99Mon 9/20/990%
65Process Detail: Prepare videotapes, flow charts, photos and documents to describe current and improved line process.32 hrs5 daysTue 9/14/99Mon 9/20/990%
1IE Hart- Greg20 hrs Tue 9/14/99Mon 9/20/990%
11CL Process Engineer12 hrs Tue 9/14/99Mon 9/20/990%
66Material Flow: Identify optimum material flow and material replenishment paths and methods.17.2 hrs3 daysTue 9/21/99Thu 9/23/990%
1IE Hart- Greg10 hrs Tue 9/21/99Thu 9/23/990%
11CL Process Engineer7.2 hrs Tue 9/21/99Thu 9/23/990%
67Cells, Line Balance: Design cells where applicable. Determine optimum line balance – tooling and personnel.2.4 hrs0.6 daysMon 8/9/99Mon 8/9/990%
1IE Hart- Greg1.44 hrs Mon 8/9/99Mon 8/9/990%
11CL Process Engineer0.96 hrs Mon 8/9/99Mon 8/9/990%
68Final Micro Layout: Define layout based on input. Prepare CAD layout options for review.48 hrs17 daysMon 8/9/99Tue 8/31/990%
1IE Hart- Greg40 hrs Mon 8/9/99Fri 8/13/990%
2AR Architect8 hrs Mon 8/9/99Fri 8/13/990%
69Final Layout Selection: Evaluate layout options vs. assumptions, constraints and criteria. Select a layout and obtain final approvals.15.2 hrs7 daysWed 9/1/99Thu 9/9/990%
1IE Hart- Greg8 hrs Wed 9/8/99Thu 9/9/990%
9CL Plant Manager2.4 hrs Wed 9/1/99Thu 9/2/990%
10CL Operations Manager2.4 hrs Wed 9/1/99Thu 9/2/990%
11CL Process Engineer2.4 hrs Wed 9/1/99Thu 9/2/990%
70Approvals: Obtain necessary approvals such as EPA and upper management.8 hrs17 daysMon 8/9/99Tue 8/31/990%
1IE Hart- Greg8 hrs Mon 8/9/99Fri 8/13/990%
71Phase IX: Plan Layout Transition24 hrs17 daysWed 8/18/99Thu 9/9/990%
72Move Resources: Identify needed and available resources for moves - riggers, internal personnel, office movers,equipment, etc.6 hrs1 dayWed 8/18/99Wed 8/18/990%
1IE Hart- Greg6 hrs Wed 8/18/99Wed 8/18/990%
73Production Requirements: Determine production schedule, build-ahead potential and available equipment move windows. 8 hrs2 daysThu 8/19/99Fri 8/20/990%
1IE Hart- Greg8 hrs Thu 8/19/99Fri 8/20/990%
74Move Plan: Create detailed transition plan withequipment numbers, from-to locations, resource needs, work packages and timing.10 hrs14 daysMon 8/23/99Thu 9/9/990%
1IE Hart- Greg10 hrs Wed 9/8/99Thu 9/9/990%
75 Phase X: Move into New Facility143 hrs52 daysMon 8/9/99Tue 10/19/990%
76Move Coordination: Coordinate equipment moves and rearrangements, with close-in planning and supervision.60 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg60 hrs Mon 8/9/99Tue 10/12/990%
77Employee Involvement: Involve operators and office personnel in final area setup and process refinement. 35 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg35 hrs Mon 8/9/99Tue 10/12/990%
78Process Startup: Ensure qualified and timely equipment and process startup.20 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg20 hrs Mon 8/9/99Tue 10/12/990%
79Progress Reporting: Monitor and report reconfiguration progress, conformance to schedule and expenditures vs. budget.16 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg16 hrs Mon 8/9/99Tue 10/12/990%
80Punch List: Prepare punch list of corrective actions and follow through to ensure completion.12 hrs5 daysWed 10/13/99Tue 10/19/990%
1IE Hart- Greg12 hrs Wed 10/13/99Tue 10/19/990%
81Phase XI: Construct Building Connection0 hrs1 dayWed 8/18/99Wed 8/18/990%
82Temporary Personnel Location: Relocate personnel as necessary temporarily during the move0 hrs1 dayWed 8/18/99Wed 8/18/990%
83Connecting Area Interior Walls Framing: Frame interior walls for cafeteria, locker room, entranceway and new conference rooms. 0 hrs1 dayWed 8/18/99Wed 8/18/990%
84Interior Walls Electrical: Install electrical wiring and boxes in interior walls for cafeteria, locker room, entranceway and new conference rooms.0 hrs1 dayWed 8/18/99Wed 8/18/990%
85Interior Walls Finishing: Install insulation and dry wall on interior walls for cafeteria, locker room, entranceway and new conference rooms. Tape and sand.0 hrs1 dayWed 8/18/99Wed 8/18/990%
86Painting: Paint walls and trim for cafeteria, locker room, entranceway and new conference rooms.0 hrs1 dayWed 8/18/99Wed 8/18/990%
87 PhaseXII: Rearrange Exising Facility107 hrs47 daysMon 8/9/99Tue 10/12/990%
88Move Coordination: Coordinate equipment moves and rearrangements, with close-in planning and supervision.60 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg60 hrs Mon 8/9/99Tue 10/12/990%
89Employee Involvement: Involve office personnel in final area setup and process refinement. 35 hrs47 daysMon 8/9/99Tue 10/12/990%
1IE Hart- Greg35 hrs Mon 8/9/99Tue 10/12/990%
90Punch List: Prepare punch list of corrective actions and follow through to ensure completion.12 hrs5 daysMon 8/9/99Fri 8/13/990%
1IE Hart- Greg12 hrs Mon 8/9/99Fri 8/13/990%
91Phase XIII: Follow-up106 hrs44 daysThu 8/19/99Tue 10/19/990%
92Process Opimization: Review and optimize the process to take full advantage of the new layout.80 hrs32 daysThu 8/19/99Fri 10/1/990%
1IE Hart- Greg80 hrs Thu 8/19/99Fri 10/1/990%
93Coaching: Provide coaching and input to plant supervision, engineering, operators and management.16 hrs12 daysMon 10/4/99Tue 10/19/990%
1IE Hart- Greg16 hrs Mon 10/4/99Tue 10/19/990%
94Output Verification: Ensure production and product quality levels meet requirements.10 hrs10 daysMon 10/4/99Fri 10/15/990%
1IE Hart- Greg10 hrs Mon 10/4/99Fri 10/15/990%
95Ongoing: Change Management158 hrs176 daysMon 8/9/99Mon 4/10/000%
96Communications: Develop a communications strategy. Routinely communicate with sponsors and plant personnel.8 hrs4 daysMon 8/9/99Thu 8/12/990%
1IE Hart- Greg8 hrs Mon 8/9/99Tue 8/10/990%
97Progress Reporting: Report progress and expectations regularly in newsletter, in memos and on bulletin board.50 hrs132 daysFri 8/13/99Mon 2/14/000%
1IE Hart- Greg50 hrs Fri 8/13/99Mon 2/14/000%
98Problem Mitigation: Provide a sounding board for problems and concerns. Respond promptly and properly.24 hrs132 daysFri 8/13/99Mon 2/14/000%
1IE Hart- Greg24 hrs Fri 8/13/99Mon 2/14/000%
99Benefits Tracking: Work to ensure process improvements bring expected benefits. Develop and record success measurements.40 hrs40 daysTue 2/15/00Mon 4/10/000%
1IE Hart- Greg40 hrs Tue 2/15/00Mon 4/10/000%
100Work Systems Redesign: Identify impacts to work system including such things as new roles and responsibilities, measures, communication mechanisms, decision rights, incentives and work environment. 36 hrs132 daysFri 8/13/99Mon 2/14/000%
1IE Hart- Greg36 hrs Fri 8/13/99Mon 2/14/000%